Job costing in the trades: how to find your loss-making projects

Bleno Team
Cover image: Job costing in the trades: how to find your loss-making projects

Sound familiar? The job is finished, the invoice has gone out, the customer has paid. On paper everything looks fine. But at the end of the year there is less left over than expected. Where did the money go?

The answer usually lies in the individual projects – and most trade businesses never look at them closely. Without job costing you are flying blind: you do not know which jobs make a profit and which ones cost money. In this article we show why job costing is essential for every trade business and how to do it without much effort.

What is job costing?

Job costing compares the planned costs (planned) with the costs actually incurred (actual) on a completed project. It answers a simple question: did we make money on this job – and if so, how much?

To do this, you compare:

  • Working hours: How many hours were planned, and how many were actually needed?
  • Material costs: What was estimated, and what was actually bought and installed?
  • Subcontracted work: Were subcontractors or special services planned in?
  • Other costs: Travel, machine hire, disposal – was everything taken into account?

Why most businesses do not do job costing

The reasons are always the same:

"No time"

The next job is already waiting. Once a project is finished, work moves straight on. Job costing gets postponed – and at some point forgotten.

"Too much effort"

If hours are recorded on paper and material costs sit in various folders, job costing really is a mammoth task. No wonder it does not happen.

"We know what we earn"

A dangerous fallacy. Gut feeling is deceptive – especially on projects that went well but, because of unnoticed extra costs, were barely profitable after all.

What happens without job costing

Estimating errors repeat themselves

If you do not know that a certain type of job regularly eats up more hours than estimated, you make the same mistake on the next quote. And again. And again.

Loss-making projects stay invisible

A project that brings in €500 less than it costs does not stand out in day-to-day business. But ten such projects a year? That is a €5,000 loss – without anyone noticing.

Prices are wrong

Without experience from completed projects, your quote prices are based on estimates. Price too high and you lose jobs. Price too low and you lose money. Both are avoidable.

Hidden costs stay hidden

Travel time, waiting time, rework, material offcuts – these cost items often do not appear in the initial estimate. Only job costing makes them visible.

How job costing works in practice

Requirement 1: Record hours per project

The most important basis: every working hour must be assigned to a project. If your employees fill in timesheets without a project reference, meaningful job costing is impossible.

Solution: A time-tracking app in which employees select a project when they start.

Requirement 2: Record material costs per project

Which material was bought for which project? If all material purchases end up in one big pot, material consumption cannot be allocated to individual jobs.

Solution: Record material directly in project management – quantity, price, assignment.

Requirement 3: Define planned values

Job costing needs a reference value. It comes from your quote: estimated hours, estimated material, estimated total costs. Without planned values, there is nothing to measure against.

The comparison: planned vs. actual

Once hours and material are recorded per project, the comparison is simple:

ItemPlanned (quote)ActualDifference
Working hours120 h145 h+25 h (+21%)
Material costs€4,200€4,800+€600 (+14%)
Subcontracted work€1,500€1,500€0
Total costs€12,300€14,475+€2,175
Job value€14,500
Profit€2,200€25-99%

In this example the job looked like a €2,200 profit on paper. In reality, €25 was left. Without job costing, the business would have kept taking on similar jobs with the same estimate – and wondered why nothing is left at the end of the year.

What job costing teaches you

Which types of job are profitable

After 10–20 costed projects you start to see patterns: are roof renovations more profitable than new builds? Are small jobs worth it, or large ones? Which types of customer cause the most extra work?

Where you systematically underestimate

Typical insights: "We always estimate 20% too few hours for painting work" or "We never account for material offcuts." Insights like these make future quotes more accurate.

Whether your hourly rates are right

If job costing shows that most projects end up just above zero, your hourly rates are too low. Without this data, you only notice when it is too late.

Job costing with Bleno

In Bleno, the data for job costing comes together automatically:

  • Time tracking: Hours are recorded per project via the app – assigned automatically, no manual rebooking.
  • Material management: Material is assigned to the project – with quantity and price.
  • Planned values from the quote: The estimate from the quote serves as the basis for comparison.
  • Planned vs. actual comparison: For each project you see at a glance where the differences are – hours, material and total.

No separate spreadsheet, no manual data collection. Job costing emerges from the data that is generated in everyday work anyway.

Conclusion: if you do not cost your jobs afterwards, you estimate them wrongly

Job costing is not a nice-to-have – it is the basis for realistic quote prices, profitable jobs and a healthy business. Without it, you work on assumptions instead of facts.

The effort? Minimal – if hours and material are recorded digitally anyway. The benefit? Every loss-making project you identify saves you real money next time.